PK0-003 exam questions


♥♥ 2021 NEW RECOMMEND ♥♥

Free VCE & PDF File for CompTIA PK0-003 Real Exam (Full Version!)

★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PK0-003 Exam Dumps (PDF & VCE):
Available on: http://www.surepassexam.com/PK0-003-exam-dumps.html

Q101. - (Topic 1) 

Determining how to communicate general project information with a globally dispersed team has created scheduling challenges. Which of the following would BEST remedy the situation? 

A. Provide a written forum that allows for asynchronous participation 

B. Conduct a meeting at a time where everyone is inconvenienced 

C. Schedule a meeting when the majority of the team is available 

D. Establish a conference call with all team members 

Answer:


Q102. - (Topic 2) 

Which of the following techniques provides the MOST positive outcomes to conflict? (Select THREE). 

A. Forcing 

B. Smoothing 

C. Influencing 

D. Negotiating 

E. Avoiding 

F. Convincing 

G. Socializing 

H. Compromising 

I. Confronting 

Answer: B,D,H 


Q103. - (Topic 3) 

A project manager has been tasked with leading a process improvement effort within a large manufacturing facility. Unfortunately, the budgetary constraints imposed by management have forced the team to focus only on the opportunities with likelihood of greatest benefit to the organization once the dataset is collected. Which of the following would be MOST suitable in this scenario? 

A. Scope review 

B. Pareto chart 

C. Check sheet 

D. Delphi method 

E. Ishikawa diagram 

Answer:


Q104. - (Topic 1) 

A coworker approaches the project manager regarding a project team member’s prior work ethic. Which of the following is the BEST approach for the project manager to address the information presented? 

A. Do not act on the information presented 

B. Ask the resource manager for another resource 

C. Discuss the issue with human resources 

D. Confront the resource manager about the risk 

Answer:


Q105. - (Topic 1) 

The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice? 

A. Contact the stakeholders in the project to determine the best course of action. 

B. Complete a project management change form without notifying the sponsor. 

C. Document the change to the project without informing the stakeholders. 

D. Perform an impact analysis and contact the project sponsor. 

Answer:


Q106. - (Topic 1) 

A well-written scope document will include which of the following? (Select TWO). 

A. Contact information 

B. Milestones C. Stakeholders 

D. Constraints 

E. Project acceptance criteria 

F. Project tasks 

Answer: D,E 


Q107. - (Topic 1) 

Which of the following risk responses would be characterized by having knowledge of a risk event and taking advantage of the risk? 

A. Accepting 

B. Enhancing 

C. Exploiting 

D. Sharing 

Answer:


Q108. - (Topic 3) 

Due to organizational turnover, a project is being run by a third project manager. The project manager learns that team members believe the team is meeting too frequently and it is negatively impacting the ability of team members to complete tasks. Which of the following actions should the project manager take FIRST to determine how to get the project back on-track? 

A. Assess the project test plan to identify variances from the project’s intended scope and make adjustments. 

B. Review the project communication plan and determine what changes may be required based on team input. 

C. Evaluate the project risk register for entries relating to poor performance and initiate corrective measures. 

D. Develop an issue log to track the concerns of the project team and modify the scope as needed. 

Answer:


Q109. - (Topic 3) 

If a representative of a business requests functionality to be included in the project that was not originally included in the project scope, the project manager should refer to which of the following plans? 

A. Issue Management Plan 

B. Quality Management Plan 

C. Risk Management Plan 

D. Change Management Plan 

Answer:


Q110. - (Topic 3) 

Which of the following techniques can a project manager use to assist with quality planning? (Select THREE). 

A. Peer review 

B. Critical Chain Method (CCM) 

C. Inspection 

D. Performance Evaluation and Review Technique (PERT) 

E. Work Breakdown Structure (WBS) 

F. Benchmarking 

Answer: A,C,F