Master the 70-348 Managing Projects and Portfolios with Microsoft PPM (beta) content and be ready for exam day success quickly with this Passleader 70-348 answers. We guarantee it!We make it a reality and give you real 70-348 questions in our Microsoft 70-348 braindumps.Latest 100% VALID Microsoft 70-348 Exam Questions Dumps at below page. You can use our Microsoft 70-348 braindumps and pass your exam.

Online 70-348 free questions and answers of New Version:

NEW QUESTION 1
HOTSPOT
You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project’s Gantt chart.
70-348 dumps exhibit
Use the drop-down menus to select the answer choice that answers each question.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 2
DRAG DROP
You are an administrator for your company’s Microsoft PPM environment. You implement several project level enterprise custom fields and add these fields to new and existing views.
Some users report they spend too much time scrolling left and right in a view named Team Status. You determine that the column width for the Enterprise Project Type field may be causing the issue.
You need to reduce the amount of scrolling.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 3
You are the administrator for an organization that uses Microsoft PPM. The IT department has 10 developers. You assign all developers to a team named Developers. The IT manager plans to use the team feature of Microsoft PPM.
You need to ensure that all project managers can use Team assign instead of Resource assign.
What should you do to finish the Developers team configuration?

  • A. Create a generic resource named Developers that is not assigned to the Developers tea
  • B. Select the Team Assignment Pool option for the resource.
  • C. Create a generic resource named Developers.
  • D. Create a generic resource named Developer
  • E. Assign the resource to the Developers team.
  • F. Create a generic resource named Developers that is assigned to the Developers tea
  • G. Select the Team Assignment Pool option for the resource.

Answer: D

Explanation:
References:
http://www.mpug.com/articles/working-teams-project-onlineproject-server-2013/

NEW QUESTION 4
DRAG DROP
You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
References:
https://technet.microsoft.com/en-us/library/cc197631.aspx

NEW QUESTION 5
DRAG DROP
You are project manager in your company’s PMO. You have permission to manage the Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 6
DRAG DROP
You are a product manager in an organization that is using Microsoft PPM. Some of your resources update their assignments correctly.
You need to accept their updates without review by setting up an approval rule.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 7
HOTSPOT
You create a new project plan. You plan to take a snapshot of the project before and after the project start date.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
The first baseline happens after the planning stage of the project. It is a snapshot of the planned timescales.
At the start of a project, when the manager has all the tasks in place, the people are assigned and the money is budgeted, he creates a baseline of data for his project so that he can measure its progress.
References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-7E775482-AC84-4F4A-BBD0-592F9AC91953

NEW QUESTION 8
Your organization is using Microsoft PPM to manage and track all projects.
The Project Management Office (PMO) needs to know which of the projects are aligned to the organization’s strategic objectives.
You need to configure Microsoft PPM to use Portfolio Analysis.
Which two activities should you perform? Each correct answer presents part of the solution.

  • A. Set up Project Departments.
  • B. Prioritize the drivers by specifying the priority value for each driver.
  • C. Configure the Full-time Equivalent calculation.
  • D. Define business drivers.

Answer: BD

Explanation:
References:
https://technet.microsoft.com/en-us/library/dn641991.aspx

NEW QUESTION 9
You are project manager for an organization that is uses Microsoft PPM. You need to create a project deliverable for the current project.
What should you do?

  • A. In Microsoft Project, manage a deliverable.
  • B. On the project site, edit the list to include the Task ID attribute.
  • C. In Microsoft Project, use Sync Deliverables.
  • D. On the project site, create a new item in the Deliverables list.

Answer: D

Explanation:
References:
https://diegocampereira.com/2021/02/10/creating-deliverables-using-microsoft-project-professional-and-project-site/

NEW QUESTION 10
HOTSPOT
You use Microsoft PPM to manage projects. You plan to use milestones in a project.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 11
You are a project manager for an organization that uses Microsoft PPM.
One of the project members creates a risk. You need to link the risk to a task.
What should you do?

  • A. On the Risk list, edit the project member risk and insert the identifier for the task that you must relate.
  • B. On the Risk list, enter in the details of the project member risk.
  • C. On the Schedule page, select Link Tasks.
  • D. On the Schedule page, select Related Items.

Answer: D

Explanation:
References:
https://pwmather.wordpress.com/2013/04/24/projectserver-2013-linking-list-items-to-tasks-and-other-list-items-ps2013-sp2013/

NEW QUESTION 12
You are managing an e-commerce portal development project by using Microsoft PPM.
In order to communicate the status of your project to your stakeholders, you want to create a real time project status report using Microsoft Excel in Office Online Services.
You need to show information about your overall project status and late tasks on your status report.
What should you do?

  • A. From the Report tab in Project Pro for Office 365, select the In Progress | Late Tasks repor
  • B. Save the report as a .pdf file to the designated reports library in PWA.
  • C. From the Project Details view in PWA, change the filter to the Late Tasks filter and copy and paste the tasks into Exce
  • D. Save to the designated reports library in PWA.
  • E. From the English folder in the PWA Data Connections library, open the OData Task Data .odc data connection file.
  • F. From the Power Query tab in Excel, select the From other sources | From ODBC option to add data to the report.

Answer: C

NEW QUESTION 13
A company is using Microsoft PPM to track task progress. The company implements standard overtime and non-billable time tracking.
You observe that you cannot enter overtime hours in your current timesheet.
You need to ensure that you can enter overtime hours. What should you do?

  • A. In your timesheet, add Overtime, and then enter the overtime hours.
  • B. In your timesheet, switch to the My Work view, and then enter the overtime hours.
  • C. In your timesheet, add Non-Billable, and then enter the overtime hours.
  • D. Ask your project administrator to increase Maximum Hours per Day.
  • E. In your timesheet, add the overtime hours to your regular hours.

Answer: A

Explanation:
References:
https://www.senseiprojectsolutions.com/2021/12/23/planning-and-tracking-overtime-work/

NEW QUESTION 14
HOTSPOT
You are the project manager for a real estate management company. You are using Microsoft Project to manage the development of a new restaurant. The schedule includes a task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2021.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.
70-348 dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
70-348 dumps exhibit

NEW QUESTION 15
You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent.
You need to create a new prioritization that includes the additional business driver. What should you do?

  • A. Create a new calculated prioritizatio
  • B. Select the drivers to prioritize.
  • C. Create a new manual prioritizatio
  • D. Select the correct department, and then select the drivers to prioritize.
  • E. Create a new manual prioritizatio
  • F. Select the drivers to prioritize, enter the value for each driver, and then choose to normalize.
  • G. Create a new manual prioritizatio
  • H. Select the drivers to prioritize, and then rank the drivers sequentially.

Answer: C

Explanation:
References:
http://deltabahn.com/ppm-driver-prioritization/

NEW QUESTION 16
You are a project manager using Microsoft PPM.
You need to create a new project that uses one of your company’s templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.

  • A. From Microsoft Project, select Enterprise.
  • B. In Project Center, select New, and then select the desired enterprise project type.
  • C. In Resource Center, select New.
  • D. From Microsoft Project, select Featured.

Answer: AB

NEW QUESTION 17
......