It is more faster and easier to pass the PRINCE2-Exams book prince2 foundation exam exam by using Top Quality PRINCE2-Exams PRINCE2 Foundation exam questuins and answers. Immediate access to the Renew prince2 foundation course material free Exam and find the same core area prince2 foundation book pdf questions with professionally verified answers, then PASS your exam with a high score now.
♥♥ 2021 NEW RECOMMEND ♥♥
Free VCE & PDF File for PRINCE2-Exams PRINCE2-Foundation Real Exam (Full Version!)
★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions
Free Instant Download NEW PRINCE2-Foundation Exam Dumps (PDF & VCE):
Available on:
http://www.surepassexam.com/PRINCE2-Foundation-exam-dumps.html
Q61. - (Topic 1)
What takes place during the Closing a Project process?
A. The post-project benefits reviews are performed
B. Ownership of the project's products is transferred to the customer
C. An End Stage Report is prepared for the final stage
D. The project closure notification is reviewed and approved
Answer: B
Q62. - (Topic 1)
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Pay for the project
D. Specify the benefits of the project
Answer: B
Q63. - (Topic 2)
Which document should record the agreed amount of risk budget for a project?
A. Project Brief
B. Project Plan
C. Risk Management Strategy
D. Risk Register
Answer: B
Q64. - (Topic 2)
Which of the following statements about lines of authority and reporting are true?
1.
The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2.
If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Q65. - (Topic 2)
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Answer: B
Q66. - (Topic 2)
Which is a purpose of an End Project Report?
A. Identify individuals or groups that need to be told that the project is coming to an end
B. Review how well the project performed against the Project Initiation Documentation used to authorize it
C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
D. Ensure that key project information is archived and made secure
Answer: B
Q67. - (Topic 1)
Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
Answer: B
38. - (Topic 1)
What is the collective name for individuals or groups who may be affected by a project?
A. Customers
B. Project Support
C. Stakeholders
D. Team members
Answer: C
Q68. - (Topic 2)
Which product identifies the management stages and timescales of a project?
A. Project Brief
B. Project Product Description
C. Project Plan
D. Initiation Stage Plan
Answer: C
Q69. - (Topic 1)
What needs to be in place to ensure effective issue and change control?
A. Configuration management system
B. Manage by exception
C. Quality planning
D. Information needs for stakeholders
Answer: A
Q70. - (Topic 1)
Which is one of the six aspects of project performance that needs to be managed?
A. Progress
B. Change
C. Risk
D. Security
Answer: C
