Master the DCDC-002 BICSI Data Center Design Consultant - DCDC content and be ready for exam day success quickly with this Examcollection DCDC-002 braindumps. We guarantee it!We make it a reality and give you real DCDC-002 questions in our BICSI DCDC-002 braindumps.Latest 100% VALID BICSI DCDC-002 Exam Questions Dumps at below page. You can use our BICSI DCDC-002 braindumps and pass your exam.
Free demo questions for BICSI DCDC-002 Exam Dumps Below:
NEW QUESTION 1
What is the first preference regarding utility service, class F4?
- A. At least two circuits from one substation, same path
- B. One circuit from one substation, separate paths
- C. At least two circuits from two separate substations, diverse substation power grids and separate paths
- D. At least one circuit from two separate substations, different voltage levels
Answer: C
NEW QUESTION 2
What is the recommended front of rack aisle width?
- A. 2 feet
- B. 3 feet
- C. 4 feet
- D. 5 feet
Answer: C
NEW QUESTION 3
What electrical service feed options are there for a data center?
- A. Single Entrance/Single Pathway
- B. Single Entrance/Dual Pathway
- C. Dual Entrance/Dual Pathway
- D. All of the above
Answer: D
NEW QUESTION 4
How far should Data Center be located from Commercial Airport?
- A. At Least 3 Miles
- B. At Least 5 Miles
- C. At least 10 miles
- D. None of the above.
Answer: B
NEW QUESTION 5
What is recommended size ratio of Secure Storage Area?
- A. 5% of Computer Room Space
- B. 10% or greater than Available Floor Space
- C. 15-20% more than Computer Room's Cross Sectional Area
- D. 10% of Computer Room's Net Square Footage
- E. None Of These
Answer: D
NEW QUESTION 6
what can take up to40 percent of overall space in the equipment area?
- A. circulation and support equipment
- B. principal loads
- C. computer
- D. electrical equipments
- E. redistribution systems
- F. all of above
Answer: A
NEW QUESTION 7
What is the recommended floor loading capacity for a data center?
- A. 1000 lbs per s
- B. ft.
- C. 1250 lbs per s
- D. ft.
- E. 1500 lbs per s
- F. ft.
- G. 1750 lbs per s
- H. ft.
- I. 2000 lbs per s
- J. ft.
Answer: C
NEW QUESTION 8
what is the ANSI/TIA-942 typical range of pressure differential regarding positive pressure for data center.
- A. Less than or equal to –0,1 in water column (-25 Pa)
- B. More than -0,005 in wc (< -1,24 Pa), but less than or equal to +0,05in wc (+12,4 Pa)
- C. More than +3in wc (>746Pa),but less than or equaltto+6,in wc(1492 pa))
- D. Less Than –4,+4 inches water column(-1000 opa ,+100 <pa>)
Answer: A
NEW QUESTION 9
What IBC occupancy category are data centers placed in?
- A. Category 3
- B. Category 4
- C. Category5
- D. category6
Answer: B
NEW QUESTION 10
What is the ASHRAE TC 9.9 recommended range for humidity levels in a data center?
- A. 20-50%
- B. 40-60%
- C. 60-80%
- D. 80-100%
Answer: B
NEW QUESTION 11
What type of slope is considered too extreme for a data center site?
- A. 5%
- B. 10%
- C. 15%
- D. 20%
Answer: C
NEW QUESTION 12
Where should power cable be ran in an access floor?
- A. Hot aisle
- B. Cold aisle
- C. Above the access floor
- D. Below the access floor
Answer: B
NEW QUESTION 13
What is the low temperature that must be maintained in a data center according to NEB standards?
- A. 55 degrees
- B. 60 degrees
- C. 65 degrees
- D. 70 degrees
- E. 75 degrees
Answer: C
NEW QUESTION 14
CORRECT TEXT
What are the equipment clearance/access requirements when designing the door openings and loading dock areas for a data center?
Solution:
Clearance requirements of 10' L x 4' W x 8' H and 7500 pounds
Does this meet the goal?
- A. Yes
- B. Not Mastered
Answer: A
NEW QUESTION 15
what are 2 typical printer manufacturer environmental criteria?
- A. humidity and temperature
- B. lighting and sound level
- C. radioactivity measurement and electromagnetic interference
- D. electrical conductivity and soil contamination
Answer: A
NEW QUESTION 16
What is the appropriate fire rating requirements for a command center?
- A. 1/2 hour
- B. 1 hour
- C. 2 hours
- D. 3 hours
Answer: B
NEW QUESTION 17
What are the 3 different methods for grounding racks in a computer room?
- A. Ground bus, direct connections, bond to rack
- B. Ground conductor, surge protection, equipment rack
- C. Copper cable, conduit, flexible connector
- D. AC power, DC power, Ethernet
Answer: A
NEW QUESTION 18
......