The This field can be demanding new experimentations and innovations all the time. This kind of calls for constant improvement of knowledge with fresh ideas. So you will find always a few changes in the actual real PMI PMI-002 exam. The professionals are committed to revising the PMI PMI exam dumps timely. We ensure that we provide you with the most recent and most official and reliable PMI PMI-002 preparation supplies. We promise your wonderful achievement in the PMI PMI genuine exam by employing our professionally put together preparation materials.
2021 Aug PMI-002 test
Q311. Which of the following processes involves obtaining information (bids and proposals) from prospective sellers?
A. Procurement Planning
B. Source Selection
C. Contract Administration
D. Solicitation
Answer: D
Q312. Which of the following is output of the Plan Communications process?
A. Project records
B. Communications management plan
C. Performance reports
D. Formal acceptance
Answer: B
Q313. Correspondence, contract changes, and payment requests are ___________ of contract administration.
A. Outputs
B. Tools
C. Functions
D. InPuts
Answer: A
Q314. During the Develop Schedule process, a Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:
A. Critical Path Method, GERT, Resource Requirements
B. Resource Levelling Heuristics, Mathematical Analysis, Calendar!
C. Duration compression, Resource Leveling Heuristics, PERT
D. GERT, PERT, Leads and Lags
Answer: C
Q315. Lessons learned session should be held at what point in a project?
A. At the project conclusion
B. At key milestones
C. When risk events occur
D. When sponsor want
Answer: B

Renew PMI-002 vce:
Q316. ___________ must be measured regularly to identify variance from the plan.
A. Stakeholder requirements
B. Project performance
C. Schedule progress
D. Cost and schedule
Answer: B
Q317. Who creates the the Lessons Learned document?
A. Customers
B. Project team
C. Project Sponsor
D. Stakeholders
Answer: B
Q318. The project baseline is _______.
A. Original plans plus the approved changes
B. Important in the project initiation phase
C. Initial estimates for tasks and resource utilization
D. Original plans and the approved major changes
Answer: A
Q319. _______ is the most accurate Estimate Cost technique.
A. Parametric modelling
B. Bottom up estimating
C. Analogous estimating
D. None
Answer: B
Q320. Fast tracking involves:
A. Developing workarounds for previous problems.
B. An increase in project risk.
C. Getting people to work longer with overtime.
D. Meeting schedule objectives by adding resources.
Answer: B
see more PMI-002 dumps
