Proper study guides for Renewal PRINCE2-Exams PRINCE2 Practitioner exam certified begins with PRINCE2-Exams PRINCE2-Practitioner preparation products which designed to deliver the Approved PRINCE2-Practitioner questions by making you pass the PRINCE2-Practitioner test at your first time. Try the free PRINCE2-Practitioner demo right now.

Online PRINCE2-Practitioner free questions and answers of New Version:

NEW QUESTION 1

Which statement is an appropriate entry for the project approach heading within the Project Brief?

  • A. The initial estimates from the feasibility study will be verified during the initiation stage.
  • B. MFH must better manage suppliers' performance.
  • C. The Information Technology Division and the Facilities Division will be outsourced to a single service provider.
  • D. The Project Manager will be responsible for ensuring that the agreed project approach remains an appropriate choice.

Answer: C

NEW QUESTION 2

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.
Prince2-Practitioner dumps exhibit
Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?

  • A. Delete entry 9 because activities for controlling the project should be planned as part of Project controls in the Project Initiation Documentation.
  • B. No change to entry 9 because it describes the timing of performance reports.
  • C. Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be recorded in the Project controls section of the Project Initiation Documentation.

Answer: B

NEW QUESTION 3

Which of the following reports does not contain any information on risk?

  • A. Issue Report
  • B. Highlight report
  • C. Lessons Report
  • D. End Stage Report

Answer: A

NEW QUESTION 4
HOTSPOT
Extract from the Project Product Description (with errors)
Prince2-Practitioner dumps exhibit
Column 1 is a list of objectives. For each objective in Column 1, select from Column 2 the quality activity that addresses it. Each selection from Column 2 can be used once, more than once or not at all. Drop down the right answer.
Prince2-Practitioner dumps exhibit
Prince2-Practitioner dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
Prince2-Practitioner dumps exhibit

NEW QUESTION 5

Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Prince2-Practitioner dumps exhibit
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Prince2-Practitioner dumps exhibit
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage. Which 2 statements apply to the Planning assumptions section?

  • A. No change to entry 8 because this cannot be confirmed until all of the label designs entries have been received and an assessment made.
  • B. Move entry 8 to External dependencies because the label designs are created outside of the scope of the project.
  • C. Delete entry 9 because the photo session schedule should have been approved as part of stage 2.
  • D. Move entry 9 to External dependencies because the photo session schedule is created by the professional photographer.
  • E. Delete entry 10 because the inclusion of different members from the Engineering team in each photo should be shown in the Product Description for the photos.

Answer: AE

NEW QUESTION 6

Additional Information Product Description
Prince2-Practitioner dumps exhibit
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which statement applies to the Roles and responsibilities section?

  • A. Delete entry 9 because this should only be recorded in the Product Description.
  • B. Delete entry 10 because this is the responsibility of the quality review chair.
  • C. Delete entry 11 because only the Project Manager can update the Quality Register.
  • D. Amend entry 12 because this is the responsibility of supplier assurance.

Answer: D

NEW QUESTION 7

Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m. Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours. 7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Reporting arrangements or Problem handling and escalation sections?

  • A. Replace entry 8 with 'Checkpoint Report every Monday by 10.00 am' because Highlight Reports are intended for the Project Board.
  • B. Delete entry 9 because this level of detail is unnecessary.
  • C. Move entry 10 to Problem handling and escalation because that section describes how issues are handled.
  • D. Add 'Any risks identified to be added to the Risk Register' to Reporting arrangements.
  • E. Delete entry 11 because the impact analysis should be provided when the issue is notified.

Answer: DE

NEW QUESTION 8

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Proximity heading?

  • A. Proximity categories for this project are: Imminent; Within the stage; Within the project; Beyond the project.
  • B. The risk of MFH having no outsourcing experience will be categorized as Stage 4proximity.
  • C. Imminent risks are those which may occur within two weeks.
  • D. Any risk with a proximity category of imminent will be estimated as having a very high impact.
  • E. The risk of staff leaving the organization will be categorized as beyond the project proximity.

Answer: CD

NEW QUESTION 9

There are four steps in the Risk Management procedure, what are they?

  • A. Identify, Assess, Resource, Implement
  • B. Identify, Evaluate, Resource, Implement
  • C. Identify, Assess, Plan, Implement
  • D. Identify, Evaluate, Plan, Implement

Answer: C

NEW QUESTION 10

Which of the following roles cannot be combined?

  • A. Executive and Senior User
  • B. Project Manager and Project Support
  • C. Project Assurance and Team Manager
  • D. Senior Suppler and Supplier Assurance

Answer: C

NEW QUESTION 11

Who is responsible for confirming stage and project progress against agreed tolerances?

  • A. Project Support
  • B. Executive
  • C. Project Assurance
  • D. Project Manager

Answer: C

NEW QUESTION 12

Which statement best explains the purpose of Tailor to suit the project environment?

  • A. Ensure project controls are based on project's scale, complexity, importance, capability and risk
  • B. To use a set of pre-defined templates for the size of project
  • C. To tailor the use of the principles to suit the project
  • D. To pick which PRINCE2 processes to apply and which to leave out

Answer: D

NEW QUESTION 13
HOTSPOT
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Prince2-Practitioner dumps exhibit
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Prince2-Practitioner dumps exhibit
Using the Product Summary and Product Breakdown Structure provided as additional Information for this question In the Scenario Booklet, answer the following question.
Column 1 is a list of some of the entries in the product breakdown structure. Determine whether each entry in Column 1 has been correctly shown in the product breakdown structure. Select from Column 2 the appropriate statement that correctly describes that entry. Each selection from Column 2 can be used once, more than once or not at all.
Prince2-Practitioner dumps exhibit
Prince2-Practitioner dumps exhibit

  • A. Mastered
  • B. Not Mastered

Answer: A

Explanation:
Prince2-Practitioner dumps exhibit

NEW QUESTION 14

Which principle is central to the quality theme and provides explicit understanding of what the project will create?

  • A. Manage by stages
  • B. Focus on products
  • C. Manage by exception
  • D. Learn from experience

Answer: B

NEW QUESTION 15

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
✑ Design for each month - correctly showing at public holidays and new company logo
✑ Selected photographs- 12 professionally-produced photographs, showing different
members of staff
✑ Selected paper and selected envelope - for printing and mailing the calendar
✑ Chosen label design - a competition to design a label will be held as part of this project
✑ List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
✑ Create the customer fast using information from the Accounts and Marketing departments
✑ Confirm compliance with the Data Protection Legislation
✑ Create a design for each month - this will be done by the internal creative team
✑ Select and appoint a professional photographer
✑ Gather photograph design ideas from previous project and agree photographic session schedule
✑ Prepare a production cost forecast
✑ Select paper and envelope.
Stage 3 will include the activities to:
✑ Produce and select tie professionally-taken photographs
✑ Hold the label design competition and choose the label design
✑ Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?

  • A. The tolerances stated in the Project Plan CANNOT be changed.
  • B. The Executive needs to seek formal approval from corporate management to implement this change.
  • C. The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.
  • D. The revision of the Project Plan would have to wait until the end stage assessment of stage 2.

Answer: B

NEW QUESTION 16

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.
According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the configuration management procedure is correct?

  • A. The MFH Quality Manager should administer the configuration management procedure on this project because this task should always be assigned to corporate or programme management.
  • B. The MFH Quality Manager should only administer the configuration management procedure on one project at a tim
  • C. If the MFH Quality Manager already performs this task on another project, another individual should be appointed.
  • D. The MFH Quality Manager would be suitable to perform this task because he is the author of the document control process and is likely to have the knowledge required for this role.

Answer: C

NEW QUESTION 17
......

P.S. Dumpscollection.com now are offering 100% pass ensure PRINCE2-Practitioner dumps! All PRINCE2-Practitioner exam questions have been updated with correct answers: https://www.dumpscollection.net/dumps/PRINCE2-Practitioner/ (282 New Questions)