Cause all that matters here is passing the PRINCE2-Exams PRINCE2-Practitioner exam. Cause all that you need is a high score of PRINCE2-Practitioner PRINCE2 Practitioner exam exam. The only one thing you need to do is downloading Actualtests PRINCE2-Practitioner exam study guides now. We will not let you down with our money-back guarantee.

PRINCE2-Exams PRINCE2-Practitioner Free Dumps Questions Online, Read and Test Now.

NEW QUESTION 1

Which of the following should NOT be included in the business case?

  • A. Reasons
  • B. Major Risks
  • C. Business options
  • D. Business approach

Answer: D

NEW QUESTION 2

Additional Information Product Description
Prince2-Practitioner dumps exhibit
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
The service level agreement looks like any other MFH document.

  • A. Obtain agreement from the Director of Facilities Division to redesign the service level agreement within the remaining +2 days tolerance.
  • B. Raise an issue (off-specification).
  • C. Accept this error as a concession.
  • D. No action required.

Answer: D

NEW QUESTION 3

Extract from the Project Product Description (with errors)
Prince2-Practitioner dumps exhibit
Which 2 statements apply to the Development skills required section?

  • A. Move entry 13 to Composition because the appointment of the photographer is within the scope of this project.
  • B. Move entry 13 to Derivation because this is a source of information for this project.
  • C. Delete entry 14 because this skill is NOT required within this project.
  • D. Delete entry 15 because this skill is NOT required within this project.
  • E. Add 'Knowledge of Data Protection Act.

Answer: DE

NEW QUESTION 4

Extract from the Project Product Description (with errors)
Prince2-Practitioner dumps exhibit
Which 2 statements apply to the Acceptance criteria section?

  • A. Amend entry 21 to 'Appearance - 12 photos each showing different members of staff.
  • B. Move entry 21 to Composition because the photos are part of the final product.
  • C. Delete entry 22 because the development of the new company logo is not within the scope of the Calendar project.
  • D. Move entry 23 to Derivation because the Data Protection Act already exists.
  • E. Delete entry 24 because this is NOT a suitable acceptance criteria for this project.

Answer: AC

NEW QUESTION 5

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should show that the photos could be used for other promotional material for the company?

  • A. Benefits Review Plan
  • B. Lessons Log
  • C. Exception Report
  • D. End Project Report

Answer: D

NEW QUESTION 6

Additional Information
Prince2-Practitioner dumps exhibit
Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that
provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed user assurance for this project?

  • A. Retain because they are both very positive about outsourcing the selected business functions.
  • B. Retain because their divisions will be the major users of the outsourced services and they can provide the user perspective on the impact of any proposed changes.
  • C. Remove because neither of these individuals are from the business functions to be outsourced.
  • D. Retain because selecting only one of them may cause unnecessary conflict.
  • E. Retain because they are able to help identify stakeholders and their communication requirements.

Answer: BE

NEW QUESTION 7

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.
Prince2-Practitioner dumps exhibit
Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
No Benefits Review Plan has been developed. Where should the schedule of benefit reviews be recorded?

  • A. As deliverables of the project, all benefit reviews should be scheduled and documented in the Project Plan during initiation.
  • B. Small projects do not require a schedule of benefit reviews as only one review is required towards the end of the project and this should be documented within the Business Case.
  • C. Benefit reviews should be planned and recorded in the simple PID.

Answer: C

NEW QUESTION 8

Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Prince2-Practitioner dumps exhibit
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Prince2-Practitioner dumps exhibit
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage. Which 2 statements apply to the External dependencies section?

  • A. Delete entry 5 because the new company logo is being delivered by a separate project and will be detailed in the plans for that project.
  • B. Move entry 5 to Plan prerequisites because the new company logo will influence the label designs.
  • C. Move entry 5 to Plan description because the new company logo will be delivered during stage 3.
  • D. Delete entry 6 because the customer details were used in stage 2 to create the customer list.
  • E. Delete entry 7 because it should be shown in the Product Description for the label design.

Answer: DE

NEW QUESTION 9

Having completed designing the plan, in which order should the next steps take place to produce a plan?
1. Prepare Estimates
2. Define and analyze Products
3. Prepare the schedule
4. Identify activities and dependencies

  • A. 2, 4, 3, 1
  • B. 4, 2, 1, 3
  • C. 4, 3, 2, 1
  • D. 2, 4, 1, 3

Answer: D

NEW QUESTION 10

Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.
Which 2 statements explain why the Purchasing Manager should be appointed as a Senior Supplier for this project?

  • A. He is responsible for the organization's procurement activates.
  • B. He is responsible for the performance of supplier contracts.
  • C. He was an engineer and worked in that area before taking up his current position.
  • D. He can influence the external supplier's Business Case.
  • E. He is not appropriate for the role of Executive or Senior User.

Answer: AB

NEW QUESTION 11

During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  • A. Team Plan
  • B. Checkpoint Report
  • C. Quality Register
  • D. Configuration Item Record

Answer: C

NEW QUESTION 12

Extract from the Project Product Description (with errors)
Prince2-Practitioner dumps exhibit
Which 2 statements apply to the Derivation section?

  • A. Move entry 9 to Composition because this is within the scope of the project.
  • B. Delete entry 10 because this is NOT a source product for this project.
  • C. Delete entry 11 as this is already correctly shown under Development Skills required.
  • D. Move entry 12 to Composition, because this is within the scope of this project.
  • E. Add 'Professional photographer'.

Answer: CD

NEW QUESTION 13

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

  • A. Scope, People & Resources, Benefit
  • B. Scope, Risk, Product
  • C. Risk, Benefit, Product
  • D. Scope, Risk, Benefit

Answer: A

NEW QUESTION 14

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.
Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance.
\Nhat is the next action the Project Manager should consider?

  • A. Create an Exception Report to inform the Project Board of the situation and the available options.
  • B. Update the associated Configuration Item Records with details of the Issue Report that caused the change.
  • C. Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add the activities required to deliver the new Government initiative.
  • D. Create an Exception Plan to change all of the project's products to reflect the exclusion of services provided by the Facilities Division.

Answer: A

NEW QUESTION 15

Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?

  • A. Project Support
  • B. Project Manager
  • C. Team Manager
  • D. Project Assurance

Answer: D

NEW QUESTION 16

Who would be responsible for maintaining the Configuration Item Records?

  • A. Project Manager
  • B. Project Support
  • C. Project Assurance
  • D. Team Manager

Answer: B

NEW QUESTION 17
......