Q111. - (Topic 2) 

A project manager wants to ensure that end users receive proper training prior to implementation. In which of the following documents should the project manager outline the necessary training? 

A. Work breakdown structure 

B. Transition plan 

C. Communication plan 

D. Lessons learned 

Answer:


Q112. - (Topic 3) 

Once a change request has been approved by the Change Control Board, which of the following should the project manager do FIRST? 

A. Request additional funding 

B. Perform an impact analysis 

C. Update the project plan 

D. Inform the project team 

Answer: C


Q113. - (Topic 1) 

A project has been running for four months. The planned value to this point is $100,000. The actual cost is an average of $30,000 per month. Earned value is $90,000. Which of the following is the current cost performance index? 

A. 0.75 

B. 1.25 

C. $20,000 over budget 

D. Not enough detail to determine 

Answer:


Q114. - (Topic 1) 

Which of the following are the characteristics of a project? (Select TWO). 

A. Contains a procurement plan 

B. Utilizes a chart of accounts 

C. Requires resource leveling 

D. Definitive beginning and end 

E. Produces a deliverable 

Answer: D,E 


Q115. - (Topic 2) 

While heading into a meeting to discuss the forecast of the project, it is realized that the report does not contain the EAC. The project manager decides to quickly calculate the EAC. The AC is $2,000, the PV is $4,000, the EV is $3,400, and the BAC is $50,000. Which of the following represents the EAC? 

A. $29,411.76 

B. $42,372.88 

C. $58,823.53 

D. $84,745.76 

Answer:


Q116. - (Topic 3) 

Which of the following is an example of a high-level constraint to be included in a project charter? 

A. The charter must be approved by the Chief Information Officer before planning may begin. 

B. The funding is available until December 31st of the current year. 

C. The project manager’s start date is pending. 

D. The project team will be assigned after the charter is approved. 

Answer:


Q117. - (Topic 1) 

The project team is one month away from completing the project when a vendor that is providing a key component defaults on their contract. Which of the following is the FIRST thing the project manager should do? 

A. Review the project charter. 

B. Follow the communications plan. 

C. Revise the budget. 

D. Prepare performance reports. 

Answer:


Q118. - (Topic 2) 

Which of the following would be the BEST document for determining project resourcing needs? 

A. Scope statement 

B. Work breakdown structure 

C. Project charter 

D. Quality plan 

Answer:


Q119. - (Topic 1) 

In month nine of a 12-month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the customer a more accurate assessment, the project manager calculates the Cost Variance (CV) using which of the following formulas? 

A. CV = PV – AC 

B. CV = AC – EV 

C. CV = EV – PV 

D. CV = EV – AC 

Answer:


Q120. - (Topic 2) 

Which of the following includes verifying that the project scope was satisfied and lessons learned are updated once the product has been accepted by the customer? 

A. Fast tracking 

B. Risk retirement 

C. Project closure 

D. Post mortem analysis 

Answer: