Want to know Actualtests PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study 100% Correct CompTIA PK0-003 answers to Up to the minute PK0-003 questions at Actualtests. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.


♥♥ 2021 NEW RECOMMEND ♥♥

Free VCE & PDF File for CompTIA PK0-003 Real Exam (Full Version!)

★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PK0-003 Exam Dumps (PDF & VCE):
Available on: http://www.surepassexam.com/PK0-003-exam-dumps.html

Q21. - (Topic 1) 

Which of the following risk responses is taking place when there is a design change to reduce the scope of the product? 

A. Transfer 

B. Sharing 

C. Acceptance 

D. Avoidance 

Answer:


Q22. - (Topic 3) 

Which of the following would be a reason for an organization to make rather than buy a required product? 

A. Increased quality control 

B. Reduced internal resource usage 

C. Limited manufacturing capacity 

D. Exploitation of supplier’s core competencies 

Answer:


Q23. - (Topic 1) 

Which of the following actions can be used to ensure the quality of project deliverables? 

A. Analyzing performance information 

B. Ensuring all vendors are ISO certified 

C. Updating the risk register 

D. A concise statement of work 

Answer:


Q24. - (Topic 3) 

Which of the following cost estimates are included in a project charter? 

A. Analogous 

B. High-level 

C. Bottom-up 

D. Parametric 

Answer:


Q25. - (Topic 1) 

A project manager was informed that a task will be delayed by four weeks. To determine the impact on the overall project, which of the following will the project manager need to update FIRST? 

A. WBS 

B. Risk log 

C. Project schedule 

D. Scope statement 

Answer:


Q26. - (Topic 2) 

A WBS dictionary can be used to define which of the following? 

A. Deliverables 

B. Constraints 

C. Assumptions 

D. Activities 

Answer:


Q27. - (Topic 1) 

A project manager schedules a weekly meeting to review the project schedule. The project manager is looking for an easy way to see the project tasks and review areas where tasks may overlap and are dependent on others. Which of the following would provide the project manager with the BEST project view? 

A. PERT 

B. Pareto 

C. CPM 

D. Gantt 

Answer:


Q28. - (Topic 2) 

Which of the following is MOST likely to occur during project charter development? 

A. Project manager is identified for the project 

B. Project critical path is determined 

C. Bottom-up estimates are performed 

D. Work breakdown structure is created 

Answer:


Q29. - (Topic 1) 

A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST? 

A. Prepare performance report 

B. Manage the issue 

C. Schedule a meeting 

D. Update communication plan 

Answer:


Q30. - (Topic 3) 

A project stakeholder is meeting with the project manager and expresses frustration at being left out of project status updates. The stakeholder has shared these concerns with the project sponsor and the project sponsor has requested that the project manager address the issue. Which of the following actions would be MOST appropriate for the project manager to initiate to address the issue? 

A. Inform the project sponsor that updates are being sent out according to the communication management plan and take no further action. 

B. Develop an updated stakeholder register to ensure that all stakeholders are receiving all status updates relative to the project. 

C. Add the stakeholder to the distribution list for all future status updates and ensure the stakeholder has received copies of past updates. 

D. Review the communications management plan and determine if status updates are being distributed appropriately. 

Answer: