We provide real CAPM exam questions and answers braindumps in two formats. Download PDF & Practice Tests. Pass PMI CAPM Exam quickly & easily. The CAPM PDF type is available for reading and printing. You can print more and practice many times. With the help of our PMI CAPM dumps pdf and vce product and material, you can easily pass the CAPM exam.
Online CAPM free questions and answers of New Version:
NEW QUESTION 1
A key benefit of the Manage Communications process is that it enables:
- A. The best use of communication methods.
- B. An efficient and effective communication flow.
- C. Project costs to be reduced.
- D. The best use of communication technology.
Answer: B
NEW QUESTION 2
An input to the Identify Stakeholders process is:
- A. The project management plan.
- B. The stakeholder register.
- C. Procurement documents.
- D. Stakeholder analysi
Answer: C
NEW QUESTION 3
Change requests are processed for review and disposition according to which process?
- A. Control Quality
- B. Control Scope
- C. Monitor and Control Project Work
- D. Perform Integrated Change Control
Answer: D
NEW QUESTION 4
Which Knowledge Areas include processes from the Closing Process Group?
- A. Project Quality Management and Project Time Management
- B. Project Scope Management and Project Risk Management
- C. Project Stakeholder Management and Project Cost Management
- D. Project Integration Management and Project Procurement Management
Answer: D
NEW QUESTION 5
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
- A. Resource leveling and fast tracking
- B. Fast tracking and crashing
- C. Crashing and applying leads and lags
- D. Scheduling tools and applying leads and lags
Answer: A
NEW QUESTION 6
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
- A. Push
- B. Pull
- C. Interactive
- D. Iterative
Answer: B
NEW QUESTION 7
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
- A. Enhance
- B. Share
- C. Exploit
- D. Accept
Answer: C
NEW QUESTION 8
The process of identifying specific actions to be performed to produce project deliverables is:
- A. Define Activities.
- B. Create WBS.
- C. Define Scope.
- D. Develop Schedul
Answer: A
NEW QUESTION 9
Which items are components of a project management plan?
- A. Change management plan, process improvement plan, and scope management plan
- B. Agreements, procurement management plan, and work performance information
- C. Schedule management plan, project schedule, and resource calendars
- D. Scope baseline, project statement of work, and requirements traceability matrix
Answer: A
NEW QUESTION 10
Which document in the project management plan can be updated in the Plan Procurement Management process?
- A. Budget estimates
- B. Risk matrix
- C. Requirements documentation
- D. Procurement documents
Answer: C
NEW QUESTION 11
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
- A. Plan Cost Management
- B. Plan Scope Management
- C. Plan Stakeholder Management
- D. Plan Schedule Management
Answer: C
NEW QUESTION 12
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
- A. Perform Qualitative Risk Analysis
- B. Perform Quantitative Risk Analysis
- C. Plan Risk Management
- D. Plan Risk Responses
Answer: A
NEW QUESTION 13
During which process group is the quality policy determined?
- A. Initiating
- B. Executing
- C. Planning
- D. Controlling
Answer: C
NEW QUESTION 14
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
- A. Customers.
- B. Business partners.
- C. Sellers.
- D. Functional manager
Answer: B
NEW QUESTION 15
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
- A. 100
- B. 120
- C. 1,000
- D. 1,200
Answer: A
NEW QUESTION 16
In the basic communication model, which term refers to the method that is used to convey the message?
- A. Decode
- B. Encode
- C. Medium
- D. Noise
Answer: C
NEW QUESTION 17
Which is an input to the Verify Scope process?
- A. Performance report
- B. Work breakdown structure (WBS)
- C. Requested changes
- D. Project management plan
Answer: D
NEW QUESTION 18
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
- A. Project Time Management
- B. Project Cost Management
- C. Project Scope Management
- D. Project Human Resource Management
Answer: A
NEW QUESTION 19
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
- A. Initiating
- B. Planning
- C. Executing
- D. Closing
Answer: C
NEW QUESTION 20
Change requests are an output from which Project Integration Management process?
- A. Direct and Manage Project Execution
- B. Develop Project Management Plan
- C. Close Project
- D. Develop Project Charter
Answer: A
NEW QUESTION 21
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
- A. Crashing
- B. Fast tracking
- C. Leads and lags adjustment
- D. Parallel task development
Answer: B
NEW QUESTION 22
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
- A. appetite
- B. tolerance
- C. threshold
- D. management
Answer: B
NEW QUESTION 23
......
Thanks for reading the newest CAPM exam dumps! We recommend you to try the PREMIUM Downloadfreepdf.net CAPM dumps in VCE and PDF here: https://www.downloadfreepdf.net/CAPM-pdf-download.html (704 Q&As Dumps)
