NEW QUESTION 1
How is the schedule variance calculated using the earned value technique?
- A. EV less AC
- B. AC less PV
- C. EV less PV
- D. AC less EV
Answer: C
NEW QUESTION 2
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
- A. US$S000
- B. US$9500
- C. US$10,000
- D. US$12,500
Answer: D
NEW QUESTION 3
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
- A. 100
- B. 120
- C. 1,000
- D. 1,200
Answer: A
NEW QUESTION 4
Which of the following is an output of the Define Activities process?
- A. Activity list
- B. Project plan
- C. Activity duration estimates
- D. Project schedule
Answer: A
NEW QUESTION 5
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
- A. Critical path method
- B. Critical chain method
- C. Resource leveling
- D. Schedule network analysis
Answer: B
NEW QUESTION 6
Progressively elaborating high-level information into detailed plans is performed by the:
- A. project management office
- B. portfolio manager
- C. program manager
- D. project manager
Answer: D
NEW QUESTION 7
A method to manage stakeholder expectations in the scope statement is to clearly:
- A. state the guiding principles of the organization.
- B. identify alternatives to generate different approaches.
- C. state what is out of scope.
- D. outline the results of the Delphi techniqu
Answer: C
NEW QUESTION 8
Which tool or technique is used in Close Procurements?
- A. Contract plan
- B. Procurement plan
- C. Closure process
- D. Procurement audits
Answer: D
NEW QUESTION 9
Which type of dependency is contractually required or inherent in the nature of the work?
- A. External
- B. Lead
- C. Discretionary
- D. Mandatory
Answer: D
NEW QUESTION 10
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?
- A. Inspection
- B. Quality audits
- C. Design of experiments
- D. Root cause analysis
Answer: D
NEW QUESTION 11
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
- A. Project
- B. Scope
- C. Contract
- D. Program
Answer: A
NEW QUESTION 12
Which tool is used to develop technical details within the project management plan?
- A. Expert judgment
- B. Project management methodology
- C. Project management information system (PMIS)
- D. Project selection methods
Answer: A
NEW QUESTION 13
A project lifecycle is defined as:
- A. a collection of generally sequential and sometimes overlapping project phases.
- B. a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
- C. a recognized standard for the project management profession.
- D. the application of knowledge, skills, tools, and techniques to project activities to meet the project requirement
Answer: A
NEW QUESTION 14
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
- A. Cause and effect diagram
- B. Control charts
- C. Pareto chart
- D. Histogram
Answer: B
NEW QUESTION 15
An input to the Identify Stakeholders process is:
- A. The project management plan.
- B. The stakeholder register.
- C. Procurement documents.
- D. Stakeholder analysi
Answer: C
NEW QUESTION 16
A disadvantage associated with virtual teams is that they:
- A. Require communication technology that is not readily available.
- B. Create difficulties when including people with disabilities.
- C. Often cannot accommodate teams that work different hours or shifts.
- D. Create the possibility for misunderstandings to aris
Answer: D