NEW QUESTION 1
Which type of graphic is displayed below?
- A. Work breakdown structure
- B. Context diagram
- C. Control chart
- D. Pareto diagram
Answer: A
NEW QUESTION 2
Projects are separated into phases or subprojects; these phases include:
- A. feasibility study, concept development, design, and prototype.
- B. initiate, plan, execute, and monitor.
- C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.
- D. Identify Stakeholders, develop concept, build, and tes
Answer: A
NEW QUESTION 3
Which enterprise environmental factors are considered during Estimate Costs?
- A. Market conditions and published commercial information
- B. Company structure and market conditions
- C. Commercial information and company structure
- D. Existing human resources and market conditions
Answer: A
NEW QUESTION 4
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
- A. Applying calendars
- B. Resource leveling
- C. Resource planning
- D. Resource conflict management
Answer: B
NEW QUESTION 5
As the project progresses, which of the following is routinely collected from the project activities?
- A. Communication management activities
- B. Change requests
- C. Configuration verification and audit
- D. Work performance information
Answer: D
NEW QUESTION 6
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
- A. Decomposition
- B. Inspection
- C. Project analysis
- D. Document analysis
Answer: A
NEW QUESTION 7
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
- A. Influence/impact grid
- B. Power/influence grid
- C. Power/interest grid
- D. Salience model
Answer: C
NEW QUESTION 8
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
- A. Validate Scope.
- B. Plan Scope Management.
- C. Control Scope.
- D. Define Scop
Answer: C
NEW QUESTION 9
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
- A. Cost variance (CV)
- B. Cost performance index (CPI)
- C. Budget at completion (BAC)
- D. Variance at completion (VAC)
Answer: B
NEW QUESTION 10
The process of identifying and documenting relationships among the project activities is known as:
- A. Control Schedule.
- B. Sequence Activities.
- C. Define Activities.
- D. Develop Schedul
Answer: B
NEW QUESTION 11
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
- A. Mandatory
- B. Discretionary
- C. Internal
- D. External
Answer: A
NEW QUESTION 12
When does the project team determine which dependencies are discretionary?
- A. Before the Define Activities process
- B. During the Define Activities process
- C. Before the Sequence Activities process
- D. During the Sequence Activities process
Answer: D
NEW QUESTION 13
Which of the following is an input to the Perform Qualitative Risk Analysis process?
- A. Risk register
- B. Risk data quality assessment
- C. Risk categorization
- D. Risk urgency
Answer: A
NEW QUESTION 14
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
- A. Checksheets
- B. Histograms
- C. Flowcharts
- D. Control charts
Answer: C
NEW QUESTION 15
Which input to the Plan Risk Management process provides information on high-level risks?
- A. Project charter
- B. Enterprise environmental factors
- C. Stakeholder register
- D. Organizational process assets
Answer: A
NEW QUESTION 16
Which is an input to the Verify Scope process?
- A. Performance report
- B. Work breakdown structure (WBS)
- C. Requested changes
- D. Project management plan
Answer: D