NEW QUESTION 1
An example of a group decision-ma king technique is:
- A. Nominal group technique.
- B. Majority.
- C. Affinity diagram.
- D. Multi-criteria decision analysi
Answer: B
NEW QUESTION 2
What happens to a stakeholder's project influence over time?
- A. Increases
- B. Decreases
- C. Stays the same
- D. Has no bearing
Answer: B
NEW QUESTION 3
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
- A. Teaming
- B. Collective bargaining
- C. Sharing
- D. Working
Answer: A
NEW QUESTION 4
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
- A. Earned value management.
- B. Forecasting.
- C. Critical chain methodology.
- D. Critical path methodolog
Answer: A
NEW QUESTION 5
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
- A. Urgent information need
- B. Sensitivity of information
- C. Project environment
- D. Ease of use
Answer: C
NEW QUESTION 6
"Tailoring" is defined as the:
- A. effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.
- B. act of creating a project team with the specialized skills required to produce a required product or service.
- C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
- D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scop
Answer: A
NEW QUESTION 7
In which Project Management Process Group is the project charter developed?
- A. Monitoring and Controlling
- B. Executing
- C. Initiating
- D. Planning
Answer: C
NEW QUESTION 8
Which of the following is an input to Direct and Manage Project Execution?
- A. Performance reports
- B. Project charter
- C. Outputs from planning processes
- D. Enterprise environmental factors
Answer: D
NEW QUESTION 9
The chart below is an example of a:
- A. Responsibility assignment matrix (RAM)
- B. Work breakdown structure (WBS)
- C. RACI chart
- D. Requirements traceability matrix
Answer: D
NEW QUESTION 10
What is a tool to improve team performance?
- A. Staffing plan
- B. External feedback
- C. Performance reports
- D. Co-location
Answer: D
NEW QUESTION 11
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
- A. Bottom-up
- B. Parametric
- C. Analogous
- D. Three-point
Answer: C
NEW QUESTION 12
What is the most accurate rough order of magnitude (ROM)?
- A. In the Initiation phase, the estimate is in the range of +/- 50%.
- B. In the Planning phase, the estimate is in the range of +/- 50%.
- C. In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
- D. In the Closing phase, the estimate is in the range of +/- 15%.
Answer: A
NEW QUESTION 13
Stakeholder communication requirements should be included as a component of:
- A. enterprise environmental factors
- B. organizational process assets
- C. the project management plan
- D. the stakeholder register
Answer: C
NEW QUESTION 14
Lessons learned are created and project resources are released in which Process Group?
- A. Planning
- B. Executing
- C. Closing
- D. Initiating
Answer: C
NEW QUESTION 15
What is the name of a graphic display of project team members and their reporting relationships?
- A. Role dependencies chart
- B. Reporting flow diagram
- C. Project organization chart
- D. Project team structure diagram
Answer: C
NEW QUESTION 16
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
- A. Salience
- B. Influence/impact
- C. Power/interest
- D. Power/influence
Answer: A