NEW QUESTION 1
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
- A. Enterprise environmental factors
- B. Work performance reports
- C. Organizational process assets
- D. Context diagrams
Answer: A
NEW QUESTION 2
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
- A. manager.
- B. success.
- C. deadline.
- D. scope.
Answer: B
NEW QUESTION 3
Which item is an example of personnel assessment?
- A. Resource calendar
- B. Tight matrix
- C. Team-building activity
- D. Focus group
Answer: D
NEW QUESTION 4
Which type of analysis is used as a general management technique within the Plan Procurements process?
- A. Risk assessment analysis
- B. Make or buy analysis
- C. Contract value analysis
- D. Cost impact analysis
Answer: B
NEW QUESTION 5
Which of the following Project Communication Management processes uses performance reports as an input?
- A. Manage Stakeholder Expectations
- B. Report Performance
- C. Distribute Information
- D. Plan Communications
Answer: C
NEW QUESTION 6
Which is an example of Administer Procurements?
- A. Negotiating the contract
- B. Authorizing contractor work
- C. Developing the statement of work
- D. Establishing evaluation criteria
Answer: B
NEW QUESTION 7
Which of the following is a narrative description of products, services, or results to be delivered by a project?
- A. Project statement of work
- B. Business case
- C. Accepted deliverable
- D. Work performance information
Answer: A
NEW QUESTION 8
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost variance (CV) for Task 6? A. -2,000
- A. 1,000
- B. 2,000
Answer:
NEW QUESTION 9
Specification of both the deliverables and the processes is the focus of:
- A. Change control
- B. Configuration control
- C. Project monitoring and control
- D. Issue control
Answer: B
NEW QUESTION 10
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
- A. Project management plan.
- B. Project charter.
- C. Work breakdown structure.
- D. Stakeholder registe
Answer: B
NEW QUESTION 11
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
- A. WBS directory
- B. Activity list
- C. WBS
- D. Project schedule
Answer: C
NEW QUESTION 12
Sensitivity analysis is typically displayed as a/an:
- A. Decision tree diagram.
- B. Tornado diagram.
- C. Pareto diagram.
- D. Ishikawa diagra
Answer: B
NEW QUESTION 13
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
- A. Cost management plan.
- B. Work performance information.
- C. Quality management plan.
- D. Work breakdown structur
Answer: A
NEW QUESTION 14
An output of the Validate Scope process is:
- A. A requirements traceability matrix.
- B. The scope management plan.
- C. Work performance reports.
- D. Change request
Answer: D
NEW QUESTION 15
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
- A. Organizational breakdown structure (OBS)
- B. Work performance information
- C. Work package
- D. Work breakdown structure (WBS)
Answer: D
NEW QUESTION 16
The process for performing variance analysis may vary, depending on:
- A. scenario building, technology forecasting, and forecast by analogy.
- B. working relationships among various stakeholders and team members.
- C. application area, the standard used, and the industry,
- D. work to be completed nex
Answer: C