NEW QUESTION 1
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
- A. Variance Analysis
- B. Define Scope
- C. Verify Scope
- D. Control Scope
Answer: D
NEW QUESTION 2
Which of the following tools and techniques is used in the Develop Project Team process?
- A. Acquisitions
- B. Organizational theories
- C. Team-building activities
- D. Virtual teams
Answer: C
NEW QUESTION 3
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
- A. To the project management plan.
- B. To the risk register.
- C. In the scope verification processes.
- D. And their impact to the project in terms of time, cost, and risk.
Answer: D
NEW QUESTION 4
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
- A. Cost-reimbursable contracts
- B. Time and Material contracts (T&M)
- C. Fixed-price contracts
- D. Cost Plus Fixed Fee Contracts (CPFF)
Answer: C
NEW QUESTION 5
In which Knowledge Area is the project charter developed?
- A. Project Cost Management
- B. Project Scope Management
- C. Project Time Management
- D. Project Integration Management
Answer: D
NEW QUESTION 6
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
- A. Risk response planning
- B. Risk monitoring and control
- C. Performance reporting
- D. Manage stakeholders
Answer: B
NEW QUESTION 7
Which quality control technique illustrates the 80/20 principle?
- A. Ishikawa diagram
- B. Control chart
- C. Run chart
- D. Pareto chart
Answer: D
NEW QUESTION 8
Analytical techniques are a tool and technique of which process in Project Procurement Management?
- A. Plan Procurement Management
- B. Control Procurements
- C. Conduct Procurements
- D. Close Procurements
Answer: C
NEW QUESTION 9
Monte Carlo is which type of risk analysis technique?
- A. Probability
- B. Quantitative
- C. Qualitative
- D. Sensitivity
Answer: B
NEW QUESTION 10
At the start of a typical project life cycle, costs are:
- A. low, peak as work is carried out, and drop as the project nears the end.
- B. low, become steady as work is carried out, and increase as the project nears the end.
- C. high, drop as work is carried out, and increase as the project nears the end.
- D. high, become low as work is carried out, and drop as the project nears the end.
Answer: A
NEW QUESTION 11
Which of the following tools or techniques is used for Estimate Activity Durations?
- A. Critical path method
- B. Rolling wave planning
- C. Precedence diagramming method
- D. Parametric estimating
Answer: D
NEW QUESTION 12
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
- A. Enterprise environmental factors
- B. Work performance reports
- C. Organizational process assets
- D. Context diagrams
Answer: A
NEW QUESTION 13
Which of the following choices is a contract closure tool or technique?
- A. Contract plan
- B. Procurement plan
- C. Closure process
- D. Procurement audits
Answer: D
NEW QUESTION 14
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
- A. Push
- B. Pull
- C. Interactive
- D. Iterative
Answer: B
NEW QUESTION 15
Which of the following involves making information available to project stakeholders in a timely manner?
- A. Plan Communications
- B. Performance reporting
- C. Project status reports
- D. Distribute Information
Answer: D
NEW QUESTION 16
In which of the following types of organizations is resource availability moderate to high?
- A. Weak matrix
- B. Balanced matrix
- C. Strong matrix
- D. Projectized
Answer: C
NEW QUESTION 17
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
- A. The risk of achieving the shortened project time is increased.
- B. The critical path will have positive total float.
- C. Contingency reserves are released for redeployment by the project manager.
- D. Duration buffers are added to maintain a focus on planned activity durations.
Answer: A
NEW QUESTION 18
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
- A. Control chart
- B. Flowchart
- C. Checksheet
- D. Pareto diagram
Answer: A
NEW QUESTION 19
Which of the following is a tool or technique for the Plan Procurements process?
- A. Bidder conferences
- B. Proposal evaluation techniques
- C. Contract types
- D. Contract change control systems
Answer: C
NEW QUESTION 20
What are the key components of the communication model?
- A. Encode, message and feedback-message, medium, noise, and decode
- B. Encode, messaging technology, medium, noise, and decode
- C. Sender, message and feedback-message, medium, noise, and translate
- D. Receiver, message and feedback-message, medium, noise, and decode
Answer: A