NEW QUESTION 1
Which of the following is an output of the Distribute Information process?

  • A. Project calendar
  • B. Communications management plan
  • C. Organizational process assets updates
  • D. Project document updates

Answer: C

NEW QUESTION 2
In the Define Activities process, the schedule management plan is used to:

  • A. Capture the lessons learned from other projects for comparison.
  • B. Contain the standard activity list.
  • C. Document and support the project change requests.
  • D. Prescribe the level of detail needed to manage the work.

Answer: D

NEW QUESTION 3
Which tool or technique is used in the Estimate Costs process?

  • A. Acquisition
  • B. Earned value management
  • C. Vendor bid analysis
  • D. Forecasting

Answer: C

NEW QUESTION 4
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

  • A. Decomposition
  • B. Benchmarking
  • C. Inspection
  • D. Checklist analysis

Answer: C

NEW QUESTION 5
Which of the following events would result in a baseline update?

  • A. A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
  • B. A customer has approved a change request broadening the project scope and increasing the budget.
  • C. One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
  • D. One of the key project team resources has left the team and no replacement is available.

Answer: B

NEW QUESTION 6
The cost benefit analysis tool is used for creating:

  • A. Pareto charts.
  • B. quality metrics.
  • C. change requests,
  • D. Ishikawa diagrams.

Answer: B

NEW QUESTION 7
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

  • A. Team meetings
  • B. Subcontracting teams
  • C. Virtual teams
  • D. Teamwork

Answer: D

NEW QUESTION 8
Which is the correct formula for calculating expected activity cost for three-point estimating?

  • A. Ce = (C0 + 6Cm + Cp)/4
  • B. Ce = (6C0 + Cm + Cp)/4
  • C. Ce = (C0 + 4Cm + Cp)/6
  • D. Ce = (C0 + Cā€ž, + 4Cp) / 6

Answer: C

NEW QUESTION 9
Which of the following is an example of the simplest fixed-price contract?

  • A. Purchase requisition
  • B. Purchase order
  • C. Verbal agreement
  • D. Request for quote

Answer: B

NEW QUESTION 10
Which statement correctly describes the value of a business case?

  • A. It provides the necessary information to determine if a project is worth the required investment.
  • B. It provides for alternative dispute resolution procedures in event of contract default.
  • C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
  • D. It is used to help a project manager understand the scope of commercial advantages.

Answer: A

NEW QUESTION 11
Which of the following is a tool and technique used to monitor risk?

  • A. Technical performance measurement
  • B. Cost performance baseline
  • C. Benchmarking
  • D. Cost of quality

Answer: A

NEW QUESTION 12
PMP dumps exhibit
Which of the following is the correct network diagram for the table?

  • A. Begin-A-C-D-E-End-B-D
  • B. Begin-A-B-C-D-E-End
  • C. Begin-A-B-D-E-End A-C-D
  • D. Begin-A-C-D-E-End-B-C

Answer: A

NEW QUESTION 13
A project manager should communicate to stakeholders about resolved project issues by updating the:

  • A. project records
  • B. project reports
  • C. stakeholder notifications
  • D. stakeholder register

Answer: C

NEW QUESTION 14
Which of the following is a narrative description of products, services, or results to be delivered by a project?

  • A. Project statement of work
  • B. Business case
  • C. Accepted deliverable
  • D. Work performance information

Answer: A

NEW QUESTION 15
Which of the following is an output of Close Procurements?

  • A. Accepted deliverables
  • B. Organizational process assets updates
  • C. Managing stakeholder expectations
  • D. Performance reports

Answer: B

NEW QUESTION 16
The following is a network diagram for a project.
PMP dumps exhibit
The free float for Activity E is how many days?

  • A. 2
  • B. 3
  • C. 5
  • D. 8

Answer: C

NEW QUESTION 17
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

  • A. Requirements documentation
  • B. Requirements traceability matrix
  • C. Project management plan updates
  • D. Project documents updates

Answer: B

NEW QUESTION 18
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

  • A. The Delphi technique
  • B. Nominal group technique
  • C. Affinity diagram
  • D. Brainstorming

Answer: A

NEW QUESTION 19
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

  • A. portfolio
  • B. program
  • C. selection
  • D. sub portfolio

Answer: B

NEW QUESTION 20
Cost baseline is an output of which of the following processes?

  • A. Control Costs
  • B. Determine Budget
  • C. Estimate Costs
  • D. Estimate Activity Resources

Answer: B